Construction costs have soared in recent years, with major capital projects costing 20-30% more than they did just five years ago. In addition to rising costs, increasing complexity and limited availability of funding make one thing clear for project Owners, architects, and contractors (a term used throughout to refer to both contractors and construction managers)—they are all more exposed than ever to the vulnerabilities and complexities inherent in the planning, design, and construction of modern facilities.
Taking on a sizeable capital project ultimately comes down to managing considerable complexity and risk. The bottom line is always at stake, and numerous factors can quickly throw a project off course. To mitigate their risk, many Owners are turning their attention to the pre-construction phase of the project, in particular the budgeting and estimating process. Why? Because accurate budgeting and a solid understanding of capital costs matter more than ever. The entire outcome of a project—including its profitability—relies heavily on the accuracy of the projected construction costs. The more accurate the cost estimate, the more successful the project outcome.
The primary means by which Owners can exert more control in the critical pre-construction phase (and ultimately develop an accurate budget before design and construction begin) is by adopting a Parallel Estimating approach. Parallel Estimating involves investing in two separate cost estimates (typically one from the contractor and another from an independent cost estimator) for a basis of comparison. Not only is Parallel Estimating good business practice that helps minimize risk, it also provides the necessary checks and balances through independent verification that is so often lacking on projects today.
Parallel Estimating is the process of comparing and analyzing two cost estimates—one from the contractor and another prepared by an independent cost estimating firm—to provide independent verification. Instead of relying solely on the contractor’s estimate, the Owner also engages the services of an independent, third-party cost estimating firm to prepare the second estimate.
Preparing a second estimate is one of the single best investments Owners can make to exert more control in the pre-construction phase. Using independent verification, Parallel Estimating provides an essential double-check on project costs, ensuring greater accuracy and reducing the risk of expensive surprises. Owners, contractors, and architects can all achieve a clearer picture of actual construction costs, resulting in more informed decision-making and better project outcomes.
Instead of the traditional Design-Bid-Build delivery method (where procurement rules permit), many complex capital projects today are using non-traditional delivery methods such as Construction Management at Risk (CMAR), Design-Build, and Integrated Project Delivery (IPD). These non-traditional delivery methods aren’t constrained by the same procurement rules, allowing for better collaboration, more freedom in choosing contractors, and quicker project delivery.
Paramount in all non-traditional delivery methods is the contractor’s early involvement during pre-construction, where deliverables such as budgeting, scheduling, constructability analysis, and material procurement are emphasized. The early involvement of the contractor is essential in assisting the Owner in establishing accurate construction costs and reducing their risk of incurring unforeseen costs prior to the completion of design.
To mitigate risk for both the Owner and contractor, it is advantageous to engage the services of an independent cost estimator to confirm and validate the budget as design evolves from early schematic design through construction document phases. The benefits of engaging an independent cost estimator also protect the architect from unnecessary redesigns, which, apart from the added cost to the architect, typically result in schedule delays, threatening team chemistry and endangering the project’s viability.
Essentially, preparing an independent cost estimate helps lessen your risk and brings greater cost assurance to the project—for all parties involved.
Two Estimates: The Parallel Estimating process starts with the engagement of an independent third-party cost estimating firm contracted directly to the Owner. The independent cost estimator prepares their cost estimate, and the contractor does the same.
Work Breakdown Structure: Both the contractor and the independent cost estimator are required to organize their estimates in the same way (using a Work Breakdown Structure) so they can easily reconcile the two. Typically, each trade or CSI Division—or the Uniformat breakdown used during the early concept and schematic design phases—is compared, and all major scope, quality assumptions, and unit cost deviations are identified.
Comparison and Reconciliation: Through an in-depth line item review and subsequent discussions with all project team members (design, contractor, subcontractors, suppliers, and the independent cost estimator), adjustments are agreed upon for all line items, including allowances, contingencies, and amendments made to all estimates as required. This comparative process reflects the known design realities, market conditions, and owner directives related to unknown or incomplete designs.
Technology Helps: Tools like 3D models (BIM) and digital take-offs from 2D documents allow for a much greater degree of accuracy and the ability to review project documentation in detail to effectively identify, share, and reconcile assumptions concerning scope. Moreover, AI-driven construction estimates can leverage data-driven models, advanced algorithms, machine learning, and natural language processing to estimate construction costs.
As projects grow in complexity and funding becomes tighter, Parallel Estimating helps minimize risk and provides independent verification for projects. Some of the key benefits include:
Parallel Estimating gives the Owner better scope interpretation and eliminates scope duplication.
Parallel Estimating enables you to identify pricing assumptions and agree on allowances for incomplete design (i.e., how to handle parts of the project that aren’t fully designed yet).
Parallel Estimating process allows you to establish more accurate contingency amounts that reflect the true level of risk.
Parallel Estimating reduces the risk of cost overruns, redesigns, and schedule delays.
Realistic construction costs give all parties (Owner, architect, and contractor) confidence and peace of mind.
Using Parallel Estimating, Owners typically see a 5-10% reduction in the proposed contractor budget or GMP.
The benefits of Parallel Estimating far outweigh the additional cost of conducting an independent cost estimate, making it a worthwhile investment for the Owner. Not only does the process identify and mitigate risk, it does so in a format that benefits all parties involved, including the Owner, architect, and contractor, ultimately resulting in a better project for everyone.
A successful project outcome depends on critical attention to managing the pre-construction phase, particularly the budgeting and estimating process. For more information on construction cost estimating and our Parallel Estimating services, contact The Concord Group.
About The Author

Eamon Ryan is Chief Operating Officer at The Concord Group, specializing in construction cost estimating and cost management. With over two decades of experience across the U.S. and abroad, he oversees Concord’s cost management services and helps guide the firm’s overall growth strategy. Eamon is recognized for his expertise in delivering accurate, data-driven cost analysis that supports owners in making informed decisions on complex projects.
Share This article

The Concord Group is a development + construction consulting firm providing a comprehensive and fully integrated suite of project management controls that mitigate risk throughout the lifecycle of a project or capital program. We specialize in Owner’s Representation, Cost Estimating, Medical Equipment Planning, and Building Performance Services (including Commissioning, Facility Condition Assessments, and Sustainability Consulting).
Since 1996, our team of highly skilled construction cost consultants, project managers, owner representatives, cost estimators, medical planners, and engineers has successfully completed over 4,000 projects throughout the United States. We have built a reputation for delivering high-quality, accurate, and timely work for governmental agencies, healthcare organizations, institutional clients, and architectural/engineering firms, along with retail, residential, and property development companies.
Get the latest from The Concord Group